Using Awards to Process Sleepovers
When entering Sleepover shifts you have a few options for how you can process the sleepover.
Based on Awards set up like this Example of Schads Awards with S/O
You have the following options and depending on this
-
Book the Shift as a PM- SO - AM as three separate Shifts
-
Booked the Shit as a PM - Booking Notes with S/O and for members to add to the timesheet
-
Book a Sleepover with Start and End Time
Based on these allocations Setup you would have to do the following within your award setup
-
3 Separate Shifts - There would be no work involved but it would be 3 different timesheets as it is three separate shifts as required
-
BOOKED AS PM - This would appear as
Then once you process the awards it would split into as following
Then you would need to do the following
-
Update the 3rd split to be the correct date (following day)
-
-
BOOKED AS SL - This would appear as
Then once you process the awards it would split into as following
Then you would need to do the following
-
Change the 1 split to a PM shift
-
Change the 3 Shift Date to be correct
-
-
BOOKED AS SL WITH MIDNIGHT SPLIT -
Once you process the awards they would split into as following
Then you would need to do the following
-
Update Split 2 to be 2200-0600 - so the sleepover does not get charged twice
-
Delete Split 3
-